SAMBHOTA TIBETAN SCHOOLS SOCIETY (STSS) was set up by the Department of Education (CTA) on 16th June 1999 to look after a group of Tibetan schools in India and Bhutan. Project Cell of this office deals with the Fund Raising, through which, the old Infrastructures are upgraded and tries to provide basic physical Infrastructure to those schools which lacks such facilities. These project proposals are submitted to the Department of Education and included in INTEGRATED DEVELOPMENT PLAN - IV (2007 - 2011) of Central Tibetan Administration, Dharamsala.

The IDEA of creating this page is to have a transparency and to display holistic picture of the proposals to the Donor. We have given all the details of proposals depicting all the activities which reflect during the actual execution or implementation of the respective projects.

Those, who are interested to support any of these projects, can contact us through stsa1999@yahoo.co.in or Department of Education (Central Tibetan Administration of His Holiness XIV Dalai Lama).

----> Karma Chungdak (DIRECTOR)

IDP-IV

School Infrastructure Development Projects
Project No. Project Title Fund Requested
Rupee Dollars Status & acknowledgement
IDP-IV (5a) Additional Staff Quarter, CST Chauntra Rs.8,076,800.00 US$201920/- -
IDP-IV (5b) Additional Staff Quarter, STS Puruwala Rs.4,111,534.50 (US$102788) -
IDP-IV (5c) Additional Staff Quarter, STS Dekyiling Rs.3,183,910.00 (US$ 79598/-) -
IDP-IV (6) Boundary Wall/Fencing, STS Pokhriabong Rs.1,102,790.00 (US$27570) -
IDP-IV (8) Additional Hostel, CST Paonta Rs.6,353,000.00 (US$ 158825/-) -
IDP-IV (11) Lab and Kitchen Construction, STS Dekyiling Rs.1,446,180.00 (US$36155) -
IDP-IV (21) Expansion of Gangkyi Day School for Implementation of BEP Rs.7,978,639.00 (US$199466) COMPLETED

School Solar Water Heating System And Kitchen Upgradation Projects

S.no. Project Title Fund Requested
Rupee Dollar Status & acknowledgement
IDP-IV (13a) Solar Water Heating System, TSTS Gangtok Rs. 287,566.00 (US$7190/-) COMPLETED
IDP-IV (13b) Solar Water Heating System, CST Bhuntar Rs. 287,566.00 (US$7190/-) COMPLETED
IDP-IV (13d) Solar Water Heating System, CST Pokhriabong Rs. 287,566.00 (US$7190/-) COMPLETED
IDP-IV (13e) Solar Water Heating System, CST Shillong Rs. 287,566.00 (US$7190/-) Not Completed
IDP-IV (13c) Solar Water Heating System, Mevon Petoen School (Model School) Rs. 287,566.00 (US$7190/-) COMPLETED
IDP-IV (15) School Vehicle and Garage, CST Chauntra Rs.637,922.00 (US$15948) COMPLETED
IDP-IV (16a) Kitchen Upgradation, CST Paonta Rs.417,931.00 (US$10449/-) -
IDP-IV (16a) Solar Water Heating System, STS Paonta (Funded by TIBET FUND, New York, USA) - (US$ 14753/-) On-going
IDP-IV (16b) Kitchen Upgradation, STS Bhuntar Rs.417,931.00 (US$10449/-) -
IDP-IV (16c) Kitchen Upgradation, Petoen School Rs.417,931.00 (US$10449/-) -
IDP-IV (16d) Kitchen Upgradation, TSTS Gangtok Rs.417,931.00 (US$10449/-) -
IDP-IV (16e) Kitchen Upgradation, STS Pokhriabong Rs.417,931.00 (US$10449/-) -
IDP-IV (16f) Kitchen Upgradation, CST Chauntra Rs.417,931.00 (US$10449/-) COMPLETED

Non IDP-IV Projects

School Infrastructure Development Projects

S. No. Project Title Budget Status & acknowledgement
1 Renovation of School Building and Hostel, STS Bhuntar 488,125.00 -
2 Re-plastering of Hostel Block, CST Chauntra 78,400.00 COMPLETED
3 Classroom Furniture, CST Paonta 692,025.00 COMPLETED
4 Classroom Furniture, CST Chauntra 304,416.00 COMPLETED
5 Renovation of Boundary Wall, STS Gangtok 174,313.00 -
6 Renovation of Boundary Wall, STS Puruwala 199,360.00 -
7 Staff Quarter Renovation, CST Puruwala 234,080.00 -
8 Renovation of School Building, STS Gangtok 1,109,629.00 -
9 RCC Cupboard for Hostel, CST Chauntra 216,048.00 COMPLETED
10 Stage Construction, STS Gangtok 448,000.00 COMPLETED
11 Renovation of Staff Quarter, STS Dekyiling 196,000.00 -
12 Staff Room Furnishing, STS Shillong 58,352.00
13 Classroom Furnishing, STS Shillong 90,305.00 COMPLETED
14 Renovation of Kitchen, STS Bhuntar 270,925.00 COMPLETED

School Waste Management Projects

S. No. Project Title Budget Status & acknowledgement
1 Waste Management, STS Bhuntar 145,000.00 -
2 Waste Management, STS Shillong 145,000.00 -
3 Waste Management, TSTS Gangtok 145,000.00 -
4 Waste Management, STS Pokhriabong 145,000.00 -
5 Waste Management, STS Manali 145,000.00 -

School Cultural And Musical Instrument Projects

S. No. Project Title Budget Status & acknowledgement
1 Cultural/Musical Instrument for (CST Paonta, STS Dekyiling, STS Gangtok, CST Manali, STS Shillong, CST Bir, STS Pokhriabong, STS Puruwala, Mevon Tsuglag Petoen School, STS Gangkyi) 594,160.00> -

School Mattresses, Art And Craft, Kitchen Upgradation Projects

S. No. Project Title Budget Status & acknowledgement
1 Mattresses for Boarders, CST Chauntra 403,200.00 -
2 Mattresses for Boarders, STS Gangtok 134,400.00 COMPLETED
3 Mattresses for Boarders, STS Pokhriabong 134,400.00 COMPLETED
4 Art & Craft for 11 Schools (CST Paonta CST Chauntra, STS Dekyiling, STS Gangtok, CST Manali, STS Shillong, CST Bir, STS Pokhriabong, CST Puruwala, Mevon Tsuglag Petoen School, STS Gangkyi) 616,000.00 COMPLETED
5 Kitchen Utensil for School Kitchen (CST Paonta, CST Chauntra, TSTS Gangtok, STS Shillong and STS Pokhriabong) 196,000.00 COMPLETED

School Playground Development Project

S. No. Project Title Budget Status & acknowledgement
1 Playground Renovation, STS Puruwala 341,664.00 COMPLETED

Interested sponsors & Aid organisation can contact us through: stsa1999@yahoo.co.in Thank you.